The City's Pavement Rehabilitation project construction started October 28th. Please see links below for the street list and maps. Souza Construction will post notices of street closures 72 hours in advance.
Anticipated Schedule (weather dependent) |
Date | Activity |
10/28/24 - 1/31/25 | Crack sealing, base dig out and compaction, monument and manhole preservation |
2/3/25 - 3/21/25 | Cape and slurry seal |
3/24/25 - 4/18/25 | Striping, marking, sign installation |