The project is scheduled to commence on Monday, October 28, 2024, with the contractor mobilizing on-site on Tuesday, October 29, 2024, to verify the locations of utilities along Main Street. Horizontal directional drilling will begin on Wednesday, October 30, with drilling anticipated to be completed by the end of the week or early the following week. During this period, the bike path will be intermittently detoured from October 30 until construction is completed.
With a planned timeline of 30 working days, the project is expected to conclude by December 12, 2024, barring any weather or project delays. For questions or additional information, please contact the City Project Manager, Austin Della, at (805) 772-6266.